Capacity Planning & What-If Scenario Modeling
Objectives
- Model cluster growth, analyze capacity exhaustion timeline, and recommend infrastructure expansion using what-if scenarios.
Prerequisites
VCF lab environment deployed and operational
Lab Environment
VCF 9.0 lab environment with VCF Operations 9.0; UI paths in this lab follow VCF Operations 9.0. The 2V0-32.24 Cloud Operations 8.x exam itself targets vRealize Operations 8.6, vRealize Log Insight 8.8 and vRealize Suite Lifecycle Manager 8.8, so map any 8.x exam detail accordingly.
Tasks
Task 1 Capacity Planning & What-If Scenario Modeling
Model cluster growth, analyze capacity exhaustion timeline, and recommend infrastructure expansion using what-if scenarios.
Analyse the current capacity state.
- In VCF Operations click Assess under Capacity in the left menu and open the data center that holds the prod cluster (or open the prod cluster itself and use its Capacity tab)
- Capture: total capacity, used, free, growth rate, time remaining (the capacity engine projects from history; Reserved Capacity and the HA buffer reduce the usable figure)
- Example result: 400 GB total, 200 GB free, 10 GB/week growth, 20 weeks remaining
Scenario 1 - Do nothing (baseline).
- Projected exhaustion: 200 GB / 10 GB per week = week 20 from today
- Risk: the cluster crosses 80% used (320 GB of 400 GB, i.e. 120 GB more) at 120 GB / 10 GB per week = week 12
- Business impact: procurement lead time is 8 weeks, so order hardware by week 4 to land it before the 80% threshold, and by week 12 at the latest to land it before exhaustion
Scenario 2 - Add two hosts (300 GB memory in total). Model it in Capacity > Plan > What-If Analysis > New > Infrastructure Planning: Hyperconverged, adding two hosts of the prod host profile.
- New capacity: 400 GB + 300 GB = 700 GB
- New free: 200 GB + 300 GB = 500 GB
- Time remaining: 500 GB / 10 GB per week = week 50 from today
- Cost: 2 hosts x USD 80K = USD 160K capital
- Conclusion: extends the runway to about week 50 (roughly a year) and fits the business planning cycle
Scenario 3 - VM consolidation (reduce demand by 30 GB). Model it in What-If Analysis > New > Workload Planning: Hyperconverged, choosing Remove workloads and selecting the 20 candidate VMs from the Reclaim tab under Capacity > Optimize (idle VMs; oversized VMs are on the Rightsize tab).
- New free: 200 GB + 30 GB = 230 GB
- Growth also slows slightly once the idle VMs are gone: assume 9.5 GB per week
- Time remaining: 230 GB / 9.5 GB per week = about week 24 from today
- Cost: no capital; about 15 hours of ops time to migrate or retire the VMs
- Conclusion: buys roughly a month, not enough on its own
Scenario 4 - Hybrid (one host plus consolidation). Combine the two scenarios in What-If Analysis (one host added, 20 VMs removed) and compare the projections side by side.
- Add one host (150 GB): 400 GB + 150 GB = 550 GB
- Consolidate 20 VMs: 30 GB reduction
- New free: 350 GB + 30 GB = 380 GB
- Time remaining: 380 GB / 9.5 GB per week = week 40 from today
- Cost: 1 host (USD 80K) plus 15 hours of ops time
- Conclusion: the best balance of capital and effort
Present to Finance and leadership. Build a what-if comparison dashboard (Infrastructure Operations > Dashboards & Reports).
- Chart: time remaining in weeks for each scenario
- Table: scenario name, cost, effort, timeline impact
- Recommendation: "Scenario 4 - Hybrid (one host plus consolidation). Extends capacity to about week 40 (roughly nine months) for USD 80K and 15 hours of ops time."
Implement the recommended scenario.
- Commit the Scenario 4 What-If scenario (Capacity > Plan > Committed Scenarios) so the capacity engine reserves the planned demand
- Raise the change request: "Procure one host (150 GB memory) for the prod cluster"
- Schedule the VM consolidation (move 20 VMs to the test cluster) and run the reclaim actions from Automation Central if they are deletions or power-offs
- Validate afterwards: re-open Capacity > Assess and confirm time remaining matches the Scenario 4 projection
Validation Gate
Check: Verify lab completion
Expected: Lab exercise completed successfully
Common Errors
Final Validation
Lab completed successfully
✓ All steps completed → No errors observed
Cleanup / Restore
• Revert to snapshot if needed
Design Reflection (VCDX)
Capacity planning is a VCDX design component. Panelists test whether your design includes growth projections, procurement triggers, and seasonal capacity modeling.